70.2%complete

Equiti Tower

Equiti Tower is a building project in International City Phase 3, Dubai, by B N H Real Estate Developer. The Dubai Land Department's register puts it at 70.2% complete, with planned completion on Aug 30, 2025.

Planned completion was Aug 30, 2025. Time since: 1 year 2 months

Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 3185), which also shows the latest inspection date and photos.

Facts

Status
Past planned completion
Official progress
70.2%, as published by the Dubai Land Department
Planned completion
Aug 30, 2025
Construction start
Jun 12, 2024
Units
88
Buildings
1
Developer
B N H Real Estate Developer
Master developer
International City ( L.L.C )
Community
International City Phase 3, in DLD's area Warsan Fourth
Escrow bank
Abu Dhabi Commercial Bank
DLD project number
3185

The register describes it as: "Residental Building (G+1P+6Floors+R)"

Progress as the register reported it

SinceProgressPlanned completion
Oct 29, 202670.2%Aug 30, 2025

Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.

Off-plan sales registered

88 off-plan sales in Equiti Tower have been registered with the Dubai Land Department, worth AED 62.4 million in all, the first on Aug 1, 2025 and the latest on Aug 26, 2026. 1 of them in the last 90 days. The median price over the last 12 months was AED 11,603 per square meter (AED 1,078 per square foot).

Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.