Off-plan projects in International City Phase 3

23 projects in International City Phase 3 are registered and not yet complete, 6 of them past the planned completion date, according to the Dubai Land Department.

Not yet complete

ProjectDeveloperUnitsPlanned completionProgress
Mayflower ResidencesA J G Warsan Real Estate Development99Mar 31, 202696.1%
Tavora Residences by Jhk Heights Real Estate DevelopmentJhk Heights Real Estate Development95Dec 15, 202686.18%
Orbit Residences by Jewel 2Jewel Development&real Estate Investment147Oct 30, 202580.06%
The Maiden ResidenceTulip Althahabi Real Estate Development71Dec 31, 202573.02%
Equiti TowerB N H Real Estate Developer88Aug 30, 202570.2%
08 Life ResidencesDeniz Properties107May 31, 202664.87%
27 East End Garden Residences by Mirha Homes Real Estate DevelopmentMirha Homes Real Estate Development96Jan 31, 202740.26%
Linden ResidencesBlack Soil Real Estate Development72Dec 30, 202726.78%
Stellar Axis by Ajmal Estate DevelopersAjmal Estate Developers122Oct 1, 202626.67%
Zenith ResidencesArt of Amber Real Estate Development267Mar 1, 202824.09%
Sunlight HomesSunn and Sand Developers30Sep 30, 202722.09%
Dar Al Aiham OneDar Al Aiham Properties71Jun 30, 202720.78%
Sports View Residence 2 by Al Helal Al ZahabyAl Helal Al Zahaby Real Estate Development128Nov 10, 202913.35%
Elevia ResidencesValores Property Development106Jun 30, 20279.19%
Vio ResidencesModelux Real Estate Development87Dec 31, 20266.43%
Chapter 01 by Newbury DevelopmentsNewbury Real Estate Development127Oct 1, 20282.36%
Zyra Vista ResidencesLaraix Developers51Mar 31, 20272.12%
Greenfield by Samana DevelopersSamana310Oct 31, 20281.48%
Moonsa Residences 2Dugasta125Dec 31, 20261.01%
NestAndi Real Estate Development112Apr 1, 20270.79%
Coventry 2G F S Real Estate Development372Dec 1, 20280%
Zyra HillsLaraix Developers81Mar 30, 20280%
Park ResidencyPark Residency Real Estate Development98Jul 20, 20290%

Completed since 2024