Flora Shore by Calgary Properties
Flora Shore by Calgary Properties is a building project in Palm Deira, Dubai, by Calgary Properties. The Dubai Land Department's register puts it at 2.24% complete, with planned completion on Sep 30, 2027.
Planned completion: Sep 30, 2027. Time left: 11 months
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 3626), which also shows the latest inspection date and photos.
Facts
- Status
- Under construction
- Official progress
- 2.24%, as published by the Dubai Land Department
- Planned completion
- Sep 30, 2027
- Construction start
- Nov 17, 2025
- Units
- 76
- Buildings
- 1
- Developer
- Calgary Properties
- Master developer
- The Palm - Deira
- Community
- Palm Deira
- Escrow bank
- Al Ahli Bank of Kuwait K S C P Dubai Branch
- DLD project number
- 3626
The register describes it as: "Residential Building (U/G+G+2P+12 TYP+R)"
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Oct 29, 2026 | 2.24% | Sep 30, 2027 |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
Off-plan sales registered
40 off-plan sales in Flora Shore by Calgary Properties have been registered with the Dubai Land Department, worth AED 103 million in all, the first on Jan 26, 2026 and the latest on Oct 19, 2026. 3 of them in the last 90 days. The median price over the last 12 months was AED 26,120 per square meter (AED 2,427 per square foot).
Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.
More in Palm Deira
- The Meriva Collection Palm Deira · Crestarc Developers 0.1%Planned completion Dec 31, 2031
- Hado by Beyond Palm Deira · Sandy Shores Real Estate L.L.C S.o.c 0.01%Planned completion Jun 30, 2029
- Ellington Sands I Palm Deira · Ellington 0.37%Planned completion Dec 31, 2028
- Ellington Sands II Palm Deira · Ellington 0.38%Planned completion Dec 31, 2028
- Bay Grove Residences C - Dubai Islands Palm Deira · Dubai Islands 7.29%Planned completion Apr 10, 2028
- Beach Residences Dubai Islands Palm Deira · Nakheel 28.8%No planned date in the register