Gardenia Townhomes II
Gardenia Townhomes II is a villa project in Wasl Gate, Dubai, by Jag Development. The Dubai Land Department's register puts it at 100% complete (completed), with planned completion on Jun 1, 2024.
Completed on Sep 17, 2025, against a planned date of Jun 1, 2024.
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 2347), which also shows the latest inspection date and photos.
Facts
- Status
- Completed
- Official progress
- 100%, as published by the Dubai Land Department
- Planned completion
- Jun 1, 2024
- Construction start
- Jan 1, 2022
- Developer
- Jag Development
- Community
- Wasl Gate, in DLD's area Jabal Ali First
- Escrow bank
- Emirates NBD Bank
- DLD project number
- 2347
The register describes it as: "Nos.92 G+1,The project designed to have a concrete structure and block with internal and external finishes."
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Oct 29, 2026 | 100% | Jun 1, 2024 |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
More in Wasl Gate
- Boulevard Park 1 Wasl Gate · Jag Development 0%Planned completion Apr 30, 2030
- Boulevard Park 2 Wasl Gate · Jag Development 0%Planned completion Nov 30, 2029
- Omya Residences Wasl Gate · Pantheon 0.02%Planned completion Jun 30, 2028
- Taiyo Residences Wasl Gate · Continental Investments Lmd 12.09%Planned completion Dec 31, 2027
- Hills View at Wasl Gate Wasl Gate · Suncrest Hills Property 9.05%Planned completion Jun 30, 2028
- Hillside Residences 3 Wasl Gate · Jag Development 12.88%No planned date in the register
More by Jag Development
- Hillside Residences 2 Wasl Gate · Jag Development 18.49%No planned date in the register
- South Garden A Wasl Gate · Jag Development 16.15%Planned completion Dec 31, 2027
- South Garden B Wasl Gate · Jag Development 16.15%Planned completion Dec 31, 2027
- South Garden C Wasl Gate · Jag Development 16.15%Planned completion Dec 31, 2027
- South Garden D Wasl Gate · Jag Development 5.67%Planned completion May 31, 2028
- South Garden E Wasl Gate · Jag Development 8%Planned completion May 31, 2028