50.77%complete

Hatimi Residences by Fakhruddin

Hatimi Residences by Fakhruddin is a building project in Palm Deira, Dubai, by Fakhruddin Properties Development. The Dubai Land Department's register puts it at 50.77% complete, with planned completion on Oct 2, 2026.

Planned completion was Oct 2, 2026. Time since: 36 days

Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 2981), which also shows the latest inspection date and photos.

Facts

Status
Past planned completion
Official progress
50.77%, as published by the Dubai Land Department
Planned completion
Oct 2, 2026
Construction start
Oct 2, 2024
Units
116
Buildings
1
Developer
Fakhruddin Properties Development
Master developer
Nakheel .(P J S C)
Community
Palm Deira
Escrow bank
Emirates NBD Bank
DLD project number
2981

The register describes it as: "Residential Building (G+2P + 2 Towers (8 Floors +R+UR)).The project designed to have a concrete structure and block with internal and external finishes."

Progress as the register reported it

SinceProgressPlanned completion
Oct 29, 202650.77%Oct 2, 2026

Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.

Off-plan sales registered

99 off-plan sales in Hatimi Residences by Fakhruddin have been registered with the Dubai Land Department, worth AED 313 million in all, the first on May 29, 2024 and the latest on Aug 24, 2026. 2 of them in the last 90 days. The median price over the last 12 months was AED 37,718 per square meter (AED 3,504 per square foot).

Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.