Jumeirah Residences Emirates Towers
Jumeirah Residences Emirates Towers is a building project in Trade Center Second, Dubai, by Dhre 2 Bts. The Dubai Land Department's register puts it at 4.22% complete, with planned completion on Sep 1, 2030.
Planned completion: Sep 1, 2030. Time left: 3 years 10 months
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 3820), which also shows the latest inspection date and photos.
Facts
- Status
- Under construction
- Official progress
- 4.22%, as published by the Dubai Land Department
- Planned completion
- Sep 1, 2030
- Construction start
- Sep 1, 2025
- Units
- 754
- Buildings
- 2
- Developer
- Dhre 2 Bts
- Community
- Trade Center Second
- Escrow bank
- Mashreq Bank Psc
- DLD project number
- 3820
The register describes it as: "The project is a residential apartments located at Trade Center Second. It introduces 4 levels shared basement and ground level with buildings? entrance lobby: Tower A: 4B+G+59+R: comprising 394 units, & Tower B: 4B+G+56+R: comprising 360 units each. In total, the residences include 754 apartments, which offer a mix of unit types: 1-bedroom, 2-bedroom, 3-bedroom and 4-bedroom apartments."
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Oct 29, 2026 | 4.22% | Sep 1, 2030 |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
Off-plan sales registered
750 off-plan sales in Jumeirah Residences Emirates Towers have been registered with the Dubai Land Department, worth AED 5.05 billion in all, the first on Aug 6, 2025 and the latest on Oct 21, 2026. 2 of them in the last 90 days. The median price over the last 12 months was AED 57,942 per square meter (AED 5,383 per square foot).
Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.
More in Trade Center Second
More by Dhre 2 Bts
- Bluewaters Bay Marsa Dubai · Dhre 2 Bts 36.97%Planned completion Mar 1, 2027
- Design Quarter Business Park · Dhre 2 Bts 40.81%Planned completion Feb 25, 2027
- THE EDIT at d3 Business Park · Dhre 2 Bts 0.24%Planned completion Jan 31, 2030
- Atelis at d3 Business Park · Dhre 2 Bts 1.44%Planned completion Aug 14, 2029
- Bulgari Lighthouse Dubai Jumeira Bay · Dhre 2 Bts 80.01%Planned completion Mar 27, 2027
- Jumeirah Asora Bay La Mer · Dhre 2 Bts 4.4%Planned completion Mar 31, 2029