Design Quarter
Design Quarter is a building project in Business Park, Dubai, by Dhre 2 Bts. The Dubai Land Department's register puts it at 40.81% complete, with planned completion on Feb 25, 2027.
Planned completion: Feb 25, 2027. Time left: 4 months
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 2607), which also shows the latest inspection date and photos.
Facts
- Status
- Under construction
- Official progress
- 40.81%, as published by the Dubai Land Department
- Planned completion
- Feb 25, 2027
- Construction start
- May 25, 2023
- Units
- 564
- Buildings
- 9
- Developer
- Dhre 2 Bts
- Master developer
- Dham
- Community
- Business Park, in DLD's area Zaabeel Second
- Escrow bank
- Emirates NBD Bank
- DLD project number
- 2607
The register describes it as: "Building 1 (A1): G+7F+R, Building 2 (A2): G+5F+R, Building 3 (A3): G+5F+R, Building 4 (B1): G+2F+R, Building 5 (B2): G+2F+R, Building 6 (B3): G+2F+R, Building 7 (Tower A): 1P+28F+2MECH+R, Building 8 (Tower B): 1P+38F+2MECH+R, Building 9 (Tower C): 1P+7F+R, Shared Basement (2B+G): 2B+G, Shared Podium (Tower A,B&C): G+3P"
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Oct 29, 2026 | 40.81% | Feb 25, 2027 |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
Off-plan sales registered
568 off-plan sales in Design Quarter have been registered with the Dubai Land Department, worth AED 1.64 billion in all, the first on May 31, 2023 and the latest on Nov 5, 2026. 6 of them in the last 90 days. The median price over the last 12 months was AED 27,471 per square meter (AED 2,552 per square foot).
Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.
More in Business Park
- THE EDIT at d3 Business Park · Dhre 2 Bts 0.24%Planned completion Jan 31, 2030
- Atelis at d3 Business Park · Dhre 2 Bts 1.44%Planned completion Aug 14, 2029
- Artistry Two Residences Business Park · Select 0%Planned completion Feb 9, 2029
- Artistry One Residences Business Park · Select 0%Planned completion Feb 9, 2029
More by Dhre 2 Bts
- Jumeirah Residences Emirates Towers Trade Center Second · Dhre 2 Bts 4.22%Planned completion Sep 1, 2030
- Bluewaters Bay Marsa Dubai · Dhre 2 Bts 36.97%Planned completion Mar 1, 2027
- Bulgari Lighthouse Dubai Jumeira Bay · Dhre 2 Bts 80.01%Planned completion Mar 27, 2027
- Jumeirah Asora Bay La Mer · Dhre 2 Bts 4.4%Planned completion Mar 31, 2029
- The Acres Wadi Al Safa 7 · Dhre 2 Bts 25.15%No planned date in the register
- The Acres 3 & Estates Wadi Al Safa 7 · Dhre 2 Bts 14.87%Planned completion Nov 19, 2027