5.95%complete

Le Blanc Residence by Imtiaz

Le Blanc Residence by Imtiaz is a building project in Dubai Land Residence Complex, Dubai, by Imtiaz Cove Real Estate Development. The Dubai Land Department's register puts it at 5.95% complete, with planned completion on Oct 15, 2028.

Planned completion: Oct 15, 2028. Time left: 1 year 11 months

Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 4174), which also shows the latest inspection date and photos.

Facts

Status
Under construction
Official progress
5.95%, as published by the Dubai Land Department
Planned completion
Oct 15, 2028
Construction start
Jan 15, 2026
Units
323
Buildings
1
Developer
Imtiaz Cove Real Estate Development
Master developer
Dubai Land Residences
Community
Dubai Land Residence Complex, in DLD's area Wadi Al Safa 5
DLD project number
4174

The register describes it as: "B+G+3P+17+R - Residential Building"

Progress as the register reported it

SinceProgressPlanned completion
Oct 29, 20265.95%Oct 15, 2028

Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.

Off-plan sales registered

296 off-plan sales in Le Blanc Residence by Imtiaz have been registered with the Dubai Land Department, worth AED 311 million in all, the first on Jan 6, 2026 and the latest on Sep 23, 2026. 5 of them in the last 90 days. The median price over the last 12 months was AED 17,817 per square meter (AED 1,655 per square foot).

Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.