100%complete

MAG 330

MAG 330 is a building project in City of Arabia, Dubai, by MAG Property Development. The Dubai Land Department's register puts it at 100% complete (completed), with planned completion on Feb 1, 2026.

Completed on May 14, 2026, against a planned date of Feb 1, 2026.

Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 1854), which also shows the latest inspection date and photos.

Facts

Status
Completed
Official progress
100%, as published by the Dubai Land Department
Planned completion
Feb 1, 2026
Construction start
Mar 1, 2023
Units
654
Buildings
1
Developer
MAG Property Development
Master developer
Velora Prime Real Estate Development
Community
City of Arabia, in DLD's area Wadi Al Safa 4
Escrow bank
First Abu Dhabi Bank
DLD project number
1854

The register describes it as: "G+5P + HC/ Tech F+ 23F+R Residential.The project designed to have a concrete structure and block with internal and external finishes."

Progress as the register reported it

SinceProgressPlanned completion
Oct 29, 2026100%Feb 1, 2026

Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.

Off-plan sales registered

659 off-plan sales in MAG 330 have been registered with the Dubai Land Department, worth AED 716 million in all, the first on Mar 14, 2024 and the latest on Aug 19, 2026. 1 of them in the last 90 days. The median price over the last 12 months was AED 13,071 per square meter (AED 1,214 per square foot).

Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.