Mars Residences
Mars Residences is a building project in Dubai Sports City, Dubai, by Mars Star Real Estate Development. The Dubai Land Department's register puts it at 79.91% complete, with planned completion on Mar 23, 2024.
Planned completion was Mar 23, 2024. Time since: 2 years 8 months
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 556), which also shows the latest inspection date and photos.
Facts
- Status
- Past planned completion
- Official progress
- 79.91%, as published by the Dubai Land Department
- Planned completion
- Mar 23, 2024
- Construction start
- Apr 19, 2008
- Units
- 554
- Buildings
- 2
- Developer
- Mars Star Real Estate Development
- Master developer
- Dubai Sports City
- Community
- Dubai Sports City, in DLD's area Al Hebiah Fourth
- Escrow bank
- Emirates Islamic Bank
- DLD project number
- 556
The register describes it as: "Two freehold residential building development located at the Sport City . The buildings are designed to be 2B+G+19 storey high, formed as a concrete structure with internal and external finishes."
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Oct 29, 2026 | 79.91% | Mar 23, 2024 |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
Off-plan sales registered
187 off-plan sales in Mars Residences have been registered with the Dubai Land Department, worth AED 117 million in all, the first on Mar 3, 2009 and the latest on Sep 28, 2026. 4 of them in the last 90 days. The median price over the last 12 months was AED 9,691 per square meter (AED 900 per square foot).
Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.
More in Dubai Sports City
- Sportz by Danube Dubai Sports City · Danube 80.22%Planned Mar 30, 2026, 7 months ago
- Lime Light Twin Towers Dubai Sports City · Lime Light Real Estate Development 71.09%Planned Jun 30, 2026, 4 months ago
- ASPIRZ by Danube Dubai Sports City · Danube 5.08%Planned completion Dec 31, 2028
- Binghatti Haven Dubai Sports City · Binghatti 76.13%Planned Mar 31, 2026, 7 months ago
- The First Collection at Dubai Sports City Dubai Sports City · Tfg International Real Estate Development 65.7%Planned completion Nov 30, 2027
- Oasis Tower 2 Dubai Sports City · P A L Developments 73.89%Planned completion Jun 30, 2027