Binghatti Haven
Binghatti Haven is a building project in Dubai Sports City, Dubai, by Binghatti Developers. The Dubai Land Department's register puts it at 76.13% complete, with planned completion on Mar 31, 2026.
Planned completion was Mar 31, 2026. Time since: 7 months
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 3442), which also shows the latest inspection date and photos.
Facts
- Status
- Past planned completion
- Official progress
- 76.13%, as published by the Dubai Land Department
- Planned completion
- Mar 31, 2026
- Construction start
- Dec 17, 2024
- Units
- 501
- Buildings
- 1
- Developer
- Binghatti Developers
- Master developer
- Dubai Sports City
- Community
- Dubai Sports City, in DLD's area Al Hebiah Fourth
- Escrow bank
- Abu Dhabi Islamic Bank
- DLD project number
- 3442
The register describes it as: "B+G+2P+26 Residential Floors + Roof"
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Oct 29, 2026 | 76.13% | Mar 31, 2026 |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
Off-plan sales registered
491 off-plan sales in Binghatti Haven have been registered with the Dubai Land Department, worth AED 667 million in all, the first on May 15, 2025 and the latest on Nov 2, 2026. 19 of them in the last 90 days. The median price over the last 12 months was AED 16,021 per square meter (AED 1,488 per square foot).
Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.
More in Dubai Sports City
- Sportz by Danube Dubai Sports City · Danube 80.22%Planned Mar 30, 2026, 7 months ago
- Lime Light Twin Towers Dubai Sports City · Lime Light Real Estate Development 71.09%Planned Jun 30, 2026, 4 months ago
- ASPIRZ by Danube Dubai Sports City · Danube 5.08%Planned completion Dec 31, 2028
- Mars Residences Dubai Sports City · Mars Star Real Estate Development 79.91%Planned Mar 23, 2024, 2 years 8 months ago
- The First Collection at Dubai Sports City Dubai Sports City · Tfg International Real Estate Development 65.7%Planned completion Nov 30, 2027
- Oasis Tower 2 Dubai Sports City · P A L Developments 73.89%Planned completion Jun 30, 2027
More by Binghatti
- Binghatti Skyrise Business Bay · Binghatti 35.89%Planned completion Dec 31, 2026
- Binghatti Skyterraces Motor City · Binghatti 0%Planned completion Oct 31, 2027
- Maybach Six Meydan Racecourse Community · Binghatti 0%Planned completion Aug 31, 2027
- Binghatti Elite International Media Production Zone · Binghatti 53.25%Planned Jun 30, 2026, 4 months ago
- Binghatti Hills Dubai Science Park · Binghatti 90%No planned date in the register
- Binghatti Aquarise Business Bay · Binghatti 21.04%Planned Oct 31, 2026, 7 days ago