Nineteen Riviera Lagoon
Nineteen Riviera Lagoon is a villa community in Mohammed Bin Rashid Al Maktoum District 11, Dubai, by Riviera Properties Development. The Dubai Land Department's register puts it at 34.06% complete, with planned completion on Feb 12, 2027.
Planned completion: Feb 12, 2027. Time left: 3 months
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 2980), which also shows the latest inspection date and photos.
Facts
- Status
- Under construction
- Official progress
- 34.06%, as published by the Dubai Land Department
- Planned completion
- Feb 12, 2027
- Construction start
- Aug 12, 2024
- Villas
- 19
- Developer
- Riviera Properties Development
- Master developer
- Meydan Group
- Community
- Mohammed Bin Rashid Al Maktoum District 11, in DLD's area Wadi Al Safa 3
- Escrow bank
- United Bank Limited (management Office)
- DLD project number
- 2980
The register describes it as: "RESIDENTIAL DEVELOPMENT (19 VILLA G+2)"
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Oct 29, 2026 | 34.06% | Feb 12, 2027 |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
Off-plan sales registered
9 off-plan sales in Nineteen Riviera Lagoon have been registered with the Dubai Land Department, worth AED 229 million in all, the first on Nov 14, 2024 and the latest on Aug 27, 2025.
Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.
More in Mohammed Bin Rashid Al Maktoum District 11
- Gate Eleven Residences Mohammed Bin Rashid Al Maktoum District 11 · Amwaj 30.58%Planned completion Mar 31, 2028
- Art House Private Residences by Viva Mohammed Bin Rashid Al Maktoum District 11 · Viva Real Estate Development 0%Planned completion Feb 15, 2028
- High Best Tower Mohammed Bin Rashid Al Maktoum District 11 · True Future Real Estate Development 90.64%Planned Nov 1, 2026, 6 days ago
- Rome 3 by SD Mohammed Bin Rashid Al Maktoum District 11 · Samana 10.2%Planned completion Jun 30, 2028
- Woodland Terraces Mohammed Bin Rashid Al Maktoum District 11 · A M I S Real Estate Development 10.34%Planned completion Mar 30, 2027
- The Willows Residences Mohammed Bin Rashid Al Maktoum District 11 · Scc Vertex Property 0.74%Planned completion Jun 30, 2027