0.04%complete

Omoria Hotel Residences

Omoria Hotel Residences is a building project in Palm Deira, Dubai, by Innovate Development. The Dubai Land Department's register puts it at 0.04% complete (not started), with planned completion on Jul 31, 2028.

Planned completion: Jul 31, 2028. Time left: 1 year 9 months

Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 3469), which also shows the latest inspection date and photos.

Facts

Status
Not started
Official progress
0.04%, as published by the Dubai Land Department
Planned completion
Jul 31, 2028
Construction start
Jan 1, 2025
Units
57
Buildings
1
Developer
Innovate Development
Master developer
Nakheel .(P J S C)
Community
Palm Deira
Escrow bank
Sharjah Islamic Bank
DLD project number
3469

The register describes it as: "B+G+7"

Progress as the register reported it

SinceProgressPlanned completion
Oct 29, 20260.04%Jul 31, 2028

Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.

Off-plan sales registered

14 off-plan sales in Omoria Hotel Residences have been registered with the Dubai Land Department, worth AED 117 million in all, the first on Dec 16, 2025 and the latest on Jul 31, 2026. The median price over the last 12 months was AED 37,742 per square meter (AED 3,506 per square foot).

Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.