55.15%complete

Park Gate 2

Park Gate 2 is a villa project in Dubai Hills, Dubai, by Dubai Hills Estate. The Dubai Land Department's register puts it at 55.15% complete, with planned completion on Feb 28, 2027.

Planned completion: Feb 28, 2027. Time left: 4 months

Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 3641), which also shows the latest inspection date and photos.

Facts

Status
Under construction
Official progress
55.15%, as published by the Dubai Land Department
Planned completion
Feb 28, 2027
Construction start
Jun 17, 2025
Developer
Dubai Hills Estate
Community
Dubai Hills, in DLD's area Hadaeq Sheikh Mohammed Bin Rashid
Escrow bank
Emirates NBD Bank
DLD project number
3641

The register describes it as: "G+2 Villas consisting of 17nos"

Progress as the register reported it

SinceProgressPlanned completion
Oct 29, 202655.15%Feb 28, 2027

Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.