17.93%complete

Pearl House IV by Imtiaz

Pearl House IV by Imtiaz is a building project in Jumeirah Village Circle, Dubai, by Imtiaz Luxury Real Estate Development. The Dubai Land Department's register puts it at 17.93% complete, with planned completion on Feb 29, 2028.

Planned completion: Feb 29, 2028. Time left: 1 year 4 months

Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 4129), which also shows the latest inspection date and photos.

Facts

Status
Under construction
Official progress
17.93%, as published by the Dubai Land Department
Planned completion
Feb 29, 2028
Construction start
Oct 30, 2025
Units
211
Buildings
1
Developer
Imtiaz Luxury Real Estate Development
Master developer
Jumeirah Village
Community
Jumeirah Village Circle, in DLD's area Al Barsha South Fourth
Escrow bank
First Abu Dhabi Bank
DLD project number
4129

The register describes it as: "G+4P+13F+R - RETAIL & RESIDENTIAL"

Progress as the register reported it

SinceProgressPlanned completion
Oct 29, 202617.93%Feb 29, 2028

Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.

Off-plan sales registered

207 off-plan sales in Pearl House IV by Imtiaz have been registered with the Dubai Land Department, worth AED 255 million in all, the first on Oct 27, 2025 and the latest on Nov 2, 2026. 12 of them in the last 90 days. The median price over the last 12 months was AED 17,817 per square meter (AED 1,655 per square foot).

Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.