Pearls by Vision is a building project in Silicon Oasis, Dubai, by Vision Platinum Real Estate Development. The Dubai Land Department's register puts it at 100% complete (completed), with planned completion on Aug 10, 2025.
Completed on Aug 10, 2025, against a planned date of Aug 10, 2025.
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 3054), which also shows the latest inspection date and photos.
Facts
- Status
- Completed
- Official progress
- 100%, as published by the Dubai Land Department
- Planned completion
- Aug 10, 2025
- Construction start
- Feb 10, 2024
- Units
- 114
- Buildings
- 1
- Developer
- Vision Platinum Real Estate Development
- Master developer
- Dubai Integrated Economic Zones authority
- Community
- Silicon Oasis, in DLD's area Nadd Hessa
- Escrow bank
- Emirates Islamic Bank
- DLD project number
- 3054
The register describes it as: "Ground + 1 Podium + 9 Floors + Roof Commercial and Residential Building.The project designed to have a concrete structure and block with internal and external finishes."
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Oct 29, 2026 | 100% | Aug 10, 2025 |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
Off-plan sales registered
107 off-plan sales in Pearls by Vision have been registered with the Dubai Land Department, worth AED 124 million in all, the first on Aug 28, 2024 and the latest on Aug 13, 2025.
Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.
More in Silicon Oasis
- Timez by Danube Silicon Oasis · Danube 21.45%Planned completion Jul 31, 2028
- Tria by Deyaar Silicon Oasis · Deyaar 94.11%Planned Jun 30, 2025, 1 year 4 months ago
- Oasiz 2 by Danube Silicon Oasis · Danube 31%Planned completion Nov 30, 2027
- Oasiz 1 by Danube Silicon Oasis · Danube 30.36%Planned completion Nov 30, 2027
- The Hillgate Silicon Oasis · Ellington 3.12%Planned completion Jun 30, 2028
- Serenova Silicon Oasis · POB1 Properties 1.55%Planned completion Mar 31, 2028