Rena is a building project in Palm Deira, Dubai, by Avenew Real Estate Development. The Dubai Land Department's register puts it at 31.75% complete, with planned completion on May 15, 2027.
Planned completion: May 15, 2027. Time left: 6 months
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 3447), which also shows the latest inspection date and photos.
Facts
- Status
- Under construction
- Official progress
- 31.75%, as published by the Dubai Land Department
- Planned completion
- May 15, 2027
- Construction start
- May 15, 2025
- Units
- 64
- Buildings
- 1
- Developer
- Avenew Real Estate Development
- Master developer
- Nakheel .(P J S C)
- Community
- Palm Deira
- Escrow bank
- Dubai Islamic Bank
- DLD project number
- 3447
The register describes it as: "1B+G+7+R+UR"
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Oct 29, 2026 | 31.75% | May 15, 2027 |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
Off-plan sales registered
60 off-plan sales in Rena have been registered with the Dubai Land Department, worth AED 320 million in all, the first on Feb 24, 2025 and the latest on Oct 16, 2026. 1 of them in the last 90 days. The median price over the last 12 months was AED 35,272 per square meter (AED 3,277 per square foot).
Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.
More in Palm Deira
- The Meriva Collection Palm Deira · Crestarc Developers 0.1%Planned completion Dec 31, 2031
- Hado by Beyond Palm Deira · Sandy Shores Real Estate L.L.C S.o.c 0.01%Planned completion Jun 30, 2029
- Ellington Sands I Palm Deira · Ellington 0.37%Planned completion Dec 31, 2028
- Ellington Sands II Palm Deira · Ellington 0.38%Planned completion Dec 31, 2028
- Bay Grove Residences C - Dubai Islands Palm Deira · Dubai Islands 7.29%Planned completion Apr 10, 2028
- Beach Residences Dubai Islands Palm Deira · Nakheel 28.8%No planned date in the register
More by Avenew Real Estate Development
- Avenew888-Loom Dubai South Residential District · Avenew Real Estate Development 1.63%Planned completion Mar 31, 2028
- Avenew888 - Modo Dubai South Residential District · Avenew Real Estate Development 21.21%Planned completion Mar 15, 2028
- Silena Residences Palm Deira · Avenew Real Estate Development 3.83%Planned completion May 30, 2028
- Cheval Residences Palm Deira · Avenew Real Estate Development 0.04%Planned completion Mar 31, 2029
- Lia Palm Deira · Avenew Real Estate Development 4.06%Planned completion May 20, 2028
- Shoaq Palm Deira · Avenew Real Estate Development 8.6%Planned completion Oct 30, 2027