100%complete

Samana Santorini

Samana Santorini is a building project in Dubai Studio City, Dubai, by Samana International Real Estate Development. The Dubai Land Department's register puts it at 100% complete (completed), with planned completion on Apr 1, 2025.

Completed on Feb 22, 2026, against a planned date of Apr 1, 2025.

Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 2466), which also shows the latest inspection date and photos.

Facts

Status
Completed
Official progress
100%, as published by the Dubai Land Department
Planned completion
Apr 1, 2025
Construction start
Apr 1, 2023
Units
157
Buildings
1
Developer
Samana International Real Estate Development
Master developer
Tecom Investments
Community
Dubai Studio City, in DLD's area Al Hebiah Second
Escrow bank
Emirates NBD Bank
DLD project number
2466

The register describes it as: "B+G+4F+R,The project designed to have a concrete structure and block with internal and external finishes."

Progress as the register reported it

SinceProgressPlanned completion
Oct 29, 2026100%Apr 1, 2025

Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.

Off-plan sales registered

170 off-plan sales in Samana Santorini have been registered with the Dubai Land Department, worth AED 149 million in all, the first on Dec 7, 2022 and the latest on Feb 23, 2026. The median price over the last 12 months was AED 13,614 per square meter (AED 1,265 per square foot).

Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.