Seraph by Wadan
Seraph by Wadan is a building project in Dubai Land Residence Complex, Dubai, by Wadan Real Estate Development. The Dubai Land Department's register puts it at 20.87% complete, with planned completion on Dec 15, 2027.
Planned completion: Dec 15, 2027. Time left: 1 year 1 month
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 4109), which also shows the latest inspection date and photos.
Facts
- Status
- Under construction
- Official progress
- 20.87%, as published by the Dubai Land Department
- Planned completion
- Dec 15, 2027
- Construction start
- Dec 15, 2025
- Units
- 190
- Buildings
- 1
- Developer
- Wadan Real Estate Development
- Master developer
- Dubai Land Residences
- Community
- Dubai Land Residence Complex, in DLD's area Wadi Al Safa 5
- Escrow bank
- First Abu Dhabi Bank
- DLD project number
- 4109
The register describes it as: "2B+G+13 Floor + Roof"
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Nov 2, 2026 | 20.87% | Dec 15, 2027 |
| Oct 29, 2026 | 11.12% | Dec 15, 2027 |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
Off-plan sales registered
188 off-plan sales in Seraph by Wadan have been registered with the Dubai Land Department, worth AED 180 million in all, the first on Nov 26, 2025 and the latest on Sep 25, 2026. 2 of them in the last 90 days. The median price over the last 12 months was AED 13,713 per square meter (AED 1,274 per square foot).
Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.
More in Dubai Land Residence Complex
- Peace Lagoons by Peace Homes Dubai Land Residence Complex · Peace Homes 4.16%Planned completion Sep 30, 2028
- Samana IVY Gardens 2 Dubai Land Residence Complex · Samana 20.03%Planned completion Dec 31, 2027
- Peace Lagoons II by Peace Homes Dubai Land Residence Complex · Peace Homes 4.04%Planned completion Jan 1, 2029
- Cove Living Residence by Imtiaz Dubai Land Residence Complex · Imtiaz 47.21%Planned completion Apr 15, 2027
- Sky Line by Peace Homes Dubai Land Residence Complex · Peace Homes 0%Planned completion May 30, 2030
- Samana Boulevard Heights Dubai Land Residence Complex · Samana 2.5%Planned completion Dec 31, 2028
More by Wadan Real Estate Development
- Cybele by Wadan Dubai Land Residence Complex · Wadan Real Estate Development 2.03%Planned completion Dec 30, 2027
- Tresora by Wadan Jumeirah Village Circle · Wadan Real Estate Development 0%Planned completion Mar 30, 2028
- Nuvana by Wadan Palm Deira · Wadan Real Estate Development 24.87%Planned completion Sep 1, 2027