46.03%complete

Soho the Berkeley

Soho the Berkeley is a building project in Dubai Hills Estate, Dubai, by Soho Development. The Dubai Land Department's register puts it at 46.03% complete, with planned completion on Oct 31, 2026.

Planned completion was Oct 31, 2026. Time since: 7 days

Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 2931), which also shows the latest inspection date and photos.

Facts

Status
Past planned completion
Official progress
46.03%, as published by the Dubai Land Department
Planned completion
Oct 31, 2026
Construction start
Feb 6, 2023
Units
129
Buildings
1
Developer
Soho Development
Master developer
Dubai Hills Estate
Community
Dubai Hills Estate, in DLD's area Hadaeq Sheikh Mohammed Bin Rashid
Escrow bank
Mashreq Bank Psc
DLD project number
2931

The register describes it as: "3B+G+1P+9F+R,The project designed to have a concrete structure and block with internal and external finishes."

Progress as the register reported it

SinceProgressPlanned completion
Oct 29, 202646.03%Oct 31, 2026

Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.

Off-plan sales registered

101 off-plan sales in Soho the Berkeley have been registered with the Dubai Land Department, worth AED 226 million in all, the first on Sep 11, 2024 and the latest on Sep 30, 2026. 1 of them in the last 90 days. The median price over the last 12 months was AED 33,337 per square meter (AED 3,097 per square foot).

Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.