0%complete

Soulever' by Beyond

Soulever' by Beyond is a building project in Dubai Maritime City, Dubai, by Beyond 1 Real Estate Development. The Dubai Land Department's register puts it at 0% complete (not started), with planned completion on Dec 30, 2028.

Planned completion: Dec 30, 2028. Time left: 2 years 2 months

Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 4084), which also shows the latest inspection date and photos.

Facts

Status
Not started
Official progress
0%, as published by the Dubai Land Department
Planned completion
Dec 30, 2028
Construction start
Mar 30, 2026
Units
517
Buildings
3
Developer
Beyond 1 Real Estate Development
Master developer
Dubai Maritime City
Community
Dubai Maritime City, in DLD's area Madinat Dubai Almelaheyah
Escrow bank
Emirates NBD Bank
DLD project number
4084

The register describes it as: "Proposed 2B+G+3P+31/44 Story Mixed Use " Commercial & Residential" 2 Towers"

Progress as the register reported it

SinceProgressPlanned completion
Oct 29, 20260%Dec 30, 2028

Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.

Off-plan sales registered

231 off-plan sales in Soulever' by Beyond have been registered with the Dubai Land Department, worth AED 1.14 billion in all, the first on Oct 27, 2025 and the latest on Oct 28, 2026. 6 of them in the last 90 days. The median price over the last 12 months was AED 40,598 per square meter (AED 3,772 per square foot).

Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.