Tavora Residences by Jhk Heights Real Estate Development is a building project in International City Phase 3, Dubai, by Jhk Heights Real Estate Development. The Dubai Land Department's register puts it at 86.18% complete, with planned completion on Dec 15, 2026.
Planned completion: Dec 15, 2026. Time left: 38 days
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 3825), which also shows the latest inspection date and photos.
Facts
- Status
- Under construction
- Official progress
- 86.18%, as published by the Dubai Land Department
- Planned completion
- Dec 15, 2026
- Construction start
- Sep 5, 2024
- Units
- 95
- Buildings
- 1
- Developer
- Jhk Heights Real Estate Development
- Master developer
- Nakheel .(P J S C)
- Community
- International City Phase 3, in DLD's area Warsan Fourth
- Escrow bank
- United Bank Limited (management Office)
- DLD project number
- 3825
The register describes it as: "RESIDENTIAL BUILDING (UG / G + 1P + 4 FLOOR + ROOF) WITH SWIMMING POOL FIRST FLOOR"
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Oct 29, 2026 | 86.18% | Dec 15, 2026 |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
Off-plan sales registered
95 off-plan sales in Tavora Residences by Jhk Heights Real Estate Development have been registered with the Dubai Land Department, worth AED 73.4 million in all, the first on Aug 14, 2025 and the latest on Sep 11, 2026. 1 of them in the last 90 days. The median price over the last 12 months was AED 11,572 per square meter (AED 1,075 per square foot).
Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.
More in International City Phase 3
- Coventry 2 International City Phase 3 · G F S Real Estate Development 0%Planned completion Dec 1, 2028
- Greenfield by Samana Developers International City Phase 3 · Samana 1.48%Planned completion Oct 31, 2028
- Zenith Residences International City Phase 3 · Art of Amber Real Estate Development 24.09%Planned completion Mar 1, 2028
- Orbit Residences by Jewel 2 International City Phase 3 · Jewel Development&real Estate Investment 80.06%Planned Oct 30, 2025, 1 year ago
- Sports View Residence 2 by Al Helal Al Zahaby International City Phase 3 · Al Helal Al Zahaby Real Estate Development 13.35%Planned completion Nov 10, 2029
- Chapter 01 by Newbury Developments International City Phase 3 · Newbury Real Estate Development 2.36%Planned completion Oct 1, 2028