Teema 1 & Teema 2 is a building project in Al Yelayiss 4, Dubai, by Emaar Bawadi. The Dubai Land Department's register puts it at 8.79% complete, with planned completion on Jul 1, 2016.
Planned completion was Jul 1, 2016. Time since: 10 years 4 months
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 1373), which also shows the latest inspection date and photos.
Facts
- Status
- Past planned completion
- Official progress
- 8.79%, as published by the Dubai Land Department
- Planned completion
- Jul 1, 2016
- Construction start
- Feb 1, 2014
- Villas
- 627
- Developer
- Emaar Bawadi
- Community
- Al Yelayiss 4
- Escrow bank
- Dubai Islamic Bank
- DLD project number
- 1373
The register describes it as: "1- TEEMA 1-308 Freehold G+1 attached villas located in Al Yelayiss 4 Community. 2- TEEMA 2- 320 Freehold G+1 attached villas located in Al Yelayiss 4 Community."
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Oct 29, 2026 | 8.79% | Jul 1, 2016 |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
Off-plan sales registered
2 off-plan sales in Teema 1 & Teema 2 have been registered with the Dubai Land Department, worth AED 7.6 million in all, the first on Jan 15, 2014 and the latest on Feb 18, 2014.
Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.
More by Emaar
- The St. Regis Residences, Downtown Dubai DownTown Dubai · Emaar 76.05%Planned completion Dec 25, 2026
- Palace by the Beach Dubai Harbour · Emaar 0%Planned completion Nov 30, 2031
- Avarra by Palace Business Bay · Emaar 0.08%Planned completion Jun 30, 2031
- Bayview Dubai Harbour · Emaar 63.02%Planned completion Jul 31, 2028
- Seapoint Dubai Harbour · Emaar 36.78%Planned completion Mar 31, 2028
- Golf Point Dubai World Central · Emaar 4.78%Planned completion Oct 31, 2028