The Pulse Villas 2
The Pulse Villas 2 is a villa community in Dubai South Residential District, Dubai, by Dubai South Properties DWC. The Dubai Land Department's register puts it at 100% complete (completed), with planned completion on Jan 31, 2024.
Completed on Jan 31, 2024, against a planned date of Jan 31, 2024.
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 2279), which also shows the latest inspection date and photos.
Facts
- Status
- Completed
- Official progress
- 100%, as published by the Dubai Land Department
- Planned completion
- Jan 31, 2024
- Construction start
- Jan 31, 2022
- Villas
- 74
- Developer
- Dubai South Properties DWC
- Master developer
- Dubai Aviation City Corporation
- Community
- Dubai South Residential District, in DLD's area Madinat Al Mataar
- Escrow bank
- Dubai Islamic Bank
- DLD project number
- 2279
The register describes it as: "عددًا 74من تاون هاوس G+1 شبه المنفصلة في تكوينات 3 و 4 غرف نوم"
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Oct 29, 2026 | 100% | Jan 31, 2024 |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
Off-plan sales registered
83 off-plan sales in The Pulse Villas 2 have been registered with the Dubai Land Department, worth AED 124 million in all, the first on Jan 10, 2022 and the latest on Oct 13, 2023.
Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.
More in Dubai South Residential District
- Avenew888-Loom Dubai South Residential District · Avenew Real Estate Development 1.63%Planned completion Mar 31, 2028
- Windsor House Dubai South Residential District · Ellington 3.08%Planned completion Jul 31, 2029
- Windsor House II Dubai South Residential District · Ellington 0.6%Planned completion Jul 31, 2029
- Zura Residences Dubai South Residential District · Alyakka Developers 0%Planned completion Mar 31, 2029
- Avenew888 - Modo Dubai South Residential District · Avenew Real Estate Development 21.21%Planned completion Mar 15, 2028
- South Living Dubai South Residential District · Dubai South 88.83%Planned Feb 5, 2020, 6 years 9 months ago
More by Dubai South
- South Square Dubai World Central · Dubai South 2.62%Planned completion Jun 30, 2028
- Beachfront Gates 2 Dubai South Residential District · Dubai South 41.73%Planned completion Dec 30, 2026
- South Bay 1 Dubai South Residential District · Dubai South 93.72%Planned Mar 10, 2025, 1 year 8 months ago
- South Bay 2 Dubai South Residential District · Dubai South 93.8%Planned May 30, 2026, 5 months ago
- South Bay 3 Premium Dubai South Residential District · Dubai South 88.42%No planned date in the register
- South Bay 4 Premium Dubai South Residential District · Dubai South 85.5%No planned date in the register