Tonino Lamborghini Residences
Tonino Lamborghini Residences is a building project in Meydan Racecourse Community, Dubai, by Gulf Land Property Developers. The Dubai Land Department's register puts it at 60% complete, with planned completion on Dec 31, 2026.
Planned completion: Dec 31, 2026. Time left: 2 months
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 1941), which also shows the latest inspection date and photos.
Facts
- Status
- Under construction
- Official progress
- 60%, as published by the Dubai Land Department
- Planned completion
- Dec 31, 2026
- Construction start
- Oct 1, 2017
- Units
- 553
- Buildings
- 4
- Developer
- Gulf Land Property Developers
- Master developer
- Meydan Group
- Community
- Meydan Racecourse Community, in DLD's area Nad Al Shiba First
- Escrow bank
- Commercial Bank International
- DLD project number
- 1941
The register describes it as: "4 x residential+commercial buildings- 2 blgds x 6 floors and 2 bldgs x 11 floors with common ground and 1 podium floor, Residential. The project designed to have a concrete structure and block with internal and external finishes."
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Oct 29, 2026 | 60% | Dec 31, 2026 |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
Off-plan sales registered
272 off-plan sales in Tonino Lamborghini Residences have been registered with the Dubai Land Department, worth AED 854 million in all, the first on Jan 11, 2018 and the latest on Nov 4, 2026. 13 of them in the last 90 days. The median price over the last 12 months was AED 27,448 per square meter (AED 2,550 per square foot).
Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.
More in Meydan Racecourse Community
- Maybach Six Meydan Racecourse Community · Binghatti 0%Planned completion Aug 31, 2027
- Maybach Ultimate Luxury Meydan Racecourse Community · Binghatti 0%Planned completion Aug 31, 2027
- Project Maybach Meydan Racecourse Community · Binghatti 0%Planned completion Jun 30, 2027
- Emerge Residences Meydan Racecourse Community · N A A S Real Estate Development 21.13%Planned completion Nov 1, 2027
- Saddlewood Park Meydan Racecourse Community · Mak Developers 12.45%Planned completion Sep 30, 2027
- Flamingo Lux Residence Meydan Racecourse Community · Eminent Real Estate Development LLC-FZ 47.01%Planned May 5, 2025, 1 year 6 months ago