0%complete

Maybach Ultimate Luxury

Maybach Ultimate Luxury is a building project in Meydan Racecourse Community, Dubai, by Binghatti Developers. The Dubai Land Department's register puts it at 0% complete (not started), with planned completion on Aug 31, 2027.

Planned completion: Aug 31, 2027. Time left: 10 months

Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 4320), which also shows the latest inspection date and photos.

Facts

Status
Not started
Official progress
0%, as published by the Dubai Land Department
Planned completion
Aug 31, 2027
Construction start
Jan 14, 2026
Units
1,233
Buildings
2
Developer
Binghatti Developers
Community
Meydan Racecourse Community, in DLD's area Nad Al Shiba First
Escrow bank
Dubai Islamic Bank
DLD project number
4320

The register describes it as: "B + G + Mezz. + 5P + 19 RES.Floors(Tower A) + 25 Res.Floors (Tower B) + 1MECH. + ROOF"

Progress as the register reported it

SinceProgressPlanned completion
Oct 29, 20260%Aug 31, 2027

Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.

Off-plan sales registered

279 off-plan sales in Maybach Ultimate Luxury have been registered with the Dubai Land Department, worth AED 563 million in all, the first on Feb 3, 2026 and the latest on Oct 22, 2026. 59 of them in the last 90 days. The median price over the last 12 months was AED 39,783 per square meter (AED 3,696 per square foot).

Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.