93.01%complete

Tulip Oasis 11

Tulip Oasis 11 is a building project in Majan, Dubai, by A M E Real Estate Development. The Dubai Land Department's register puts it at 93.01% complete, with planned completion on Jun 30, 2026.

Planned completion was Jun 30, 2026. Time since: 4 months

Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 3538), which also shows the latest inspection date and photos.

Facts

Status
Past planned completion
Official progress
93.01%, as published by the Dubai Land Department
Planned completion
Jun 30, 2026
Construction start
Feb 28, 2024
Units
108
Buildings
1
Developer
A M E Real Estate Development
Master developer
Liwan
Community
Majan, in DLD's area Wadi Al Safa 3
Escrow bank
Emirates Islamic Bank
DLD project number
3538

The register describes it as: "Residential Building (G+1P+10F+R )"

Progress as the register reported it

SinceProgressPlanned completion
Oct 29, 202693.01%Jun 30, 2026

Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.

Off-plan sales registered

94 off-plan sales in Tulip Oasis 11 have been registered with the Dubai Land Department, worth AED 122 million in all, the first on Sep 1, 2025 and the latest on Oct 27, 2026. 7 of them in the last 90 days. The median price over the last 12 months was AED 14,013 per square meter (AED 1,302 per square foot).

Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.