Verdana 5
Verdana 5 is a villa community in Dubai Investment Park First, Dubai, by Reportage Plus A Real Estate Development. The Dubai Land Department's register puts it at 0.1% complete (not started), with planned completion on Sep 30, 2028.
Planned completion: Sep 30, 2028. Time left: 1 year 11 months
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 4279), which also shows the latest inspection date and photos.
Facts
- Status
- Not started
- Official progress
- 0.1%, as published by the Dubai Land Department
- Planned completion
- Sep 30, 2028
- Construction start
- Sep 30, 2025
- Villas
- 271
- Developer
- Reportage Plus A Real Estate Development
- Master developer
- Dubai Investments Park Development Co
- Community
- Dubai Investment Park First
- Escrow bank
- Commercial Bank of Dubai(psc)
- DLD project number
- 4279
The register describes it as: "12 Blocks / 271 unit ?G+1,G+2+G+3 Villas? + 1 Gym & Swimming Pool"
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Oct 29, 2026 | 0.1% | Sep 30, 2028 |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
Off-plan sales registered
113 off-plan sales in Verdana 5 have been registered with the Dubai Land Department, worth AED 178 million in all, the first on Apr 3, 2026 and the latest on Nov 5, 2026. 60 of them in the last 90 days. The median price over the last 12 months was AED 13,054 per square meter (AED 1,213 per square foot).
Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.
More in Dubai Investment Park First
- The Royal Estates PLOT.2 Dubai Investment Park First · Aristocrat Star Real Estate Development 23.75%Planned Dec 31, 2017, 8 years 10 months ago
- Verdana Residence 4 Dubai Investment Park First · Reportage 0.04%Planned completion Sep 30, 2028
- Verdana Residence 5 Dubai Investment Park First · Reportage 0%Planned completion Sep 30, 2028
- Verdana Residence 7 Dubai Investment Park First · Reportage 0%Planned completion Dec 31, 2028
- Verdana Residence 6 Dubai Investment Park First · Reportage 0%Planned completion Dec 30, 2028
- Verdana Residence 3 Dubai Investment Park First · Reportage 0.04%Planned completion Sep 30, 2028
More by Reportage
- Verdana Residence 2 Dubai Investment Park First · Reportage 20.01%Planned Apr 30, 2026, 6 months ago
- Verdana Residence Dubai Investment Park First · Reportage 96.14%Planned Dec 31, 2025, 10 months ago
- Verdana Residence 8 Dubai Investment Park First · Reportage 0%Planned completion Dec 31, 2028
- Verdana Residence 10 Dubai Investment Park First · Reportage 0%Planned completion Mar 31, 2029
- Verdana (Phase 1) Dubai Investment Park First · Reportage 94.62%Planned Dec 31, 2025, 10 months ago
- Verdana(Phase 2) Dubai Investment Park First · Reportage 93.96%Planned Dec 31, 2025, 10 months ago