Villa del Garda Residences
Villa del Garda Residences is a building project in Palm Deira, Dubai, by Riviera Vista Real Estate Development. The Dubai Land Department's register puts it at 0.02% complete (not started), with planned completion on Mar 4, 2028.
Planned completion: Mar 4, 2028. Time left: 1 year 4 months
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 4388), which also shows the latest inspection date and photos.
Facts
- Status
- Not started
- Official progress
- 0.02%, as published by the Dubai Land Department
- Planned completion
- Mar 4, 2028
- Construction start
- May 4, 2026
- Units
- 134
- Buildings
- 1
- Developer
- Riviera Vista Real Estate Development
- Master developer
- Nakheel .(P J S C)
- Community
- Palm Deira
- Escrow bank
- Al Ahli Bank of Kuwait K S C P Dubai Branch
- DLD project number
- 4388
The register describes it as: "Hotel Appartement(G+7+R) with Amenities Swimming pool, Gym@ 1st F & Restaurant @ GF."
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Oct 29, 2026 | 0.02% | Mar 4, 2028 |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
Off-plan sales registered
54 off-plan sales in Villa del Garda Residences have been registered with the Dubai Land Department, worth AED 239 million in all, the first on Apr 9, 2026 and the latest on Oct 30, 2026. 15 of them in the last 90 days. The median price over the last 12 months was AED 43,498 per square meter (AED 4,041 per square foot).
Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.
More in Palm Deira
- The Meriva Collection Palm Deira · Crestarc Developers 0.1%Planned completion Dec 31, 2031
- Hado by Beyond Palm Deira · Sandy Shores Real Estate L.L.C S.o.c 0.01%Planned completion Jun 30, 2029
- Ellington Sands I Palm Deira · Ellington 0.37%Planned completion Dec 31, 2028
- Ellington Sands II Palm Deira · Ellington 0.38%Planned completion Dec 31, 2028
- Bay Grove Residences C - Dubai Islands Palm Deira · Dubai Islands 7.29%Planned completion Apr 10, 2028
- Beach Residences Dubai Islands Palm Deira · Nakheel 28.8%No planned date in the register