Dugasta off-plan projects in Dubai
Dugasta has 5 projects registered with the Dubai Land Department and not yet complete. Of its 1 project finished since 2024, 0 finished by the planned date in the register.
Not yet complete
| Project | Community | Units | Planned completion | Progress |
|---|---|---|---|---|
| Al Haseen Residence 4 | Saih Shuaib 2 | 248 | Dec 30, 2026 | 11.76% |
| Moonsa Residences 2 | International City Phase 3 | 125 | Dec 31, 2026 | 1.01% |
| Terra Tower | Dubai Land Residence Complex | 366 | Apr 30, 2027 | 7.43% |
| Al Haseen Residence 3 | Saih Shuaib 2 | 180 | May 15, 2027 | 10.08% |
| Astra Residences | Dubai South Residential District | 108 | Aug 31, 2027 | 15.34% |
Finished since 2024
| Project | Community | Planned | Completed |
|---|---|---|---|
| MOONSA Residences | International City Phase 3 | Aug 25, 2025 | Oct 30, 2026 |
The planned date is the one in the register at completion, which may itself have been revised.