1.01%complete

Moonsa Residences 2

Moonsa Residences 2 is a building project in International City Phase 3, Dubai, by Dugasta Properties Development. The Dubai Land Department's register puts it at 1.01% complete, with planned completion on Dec 31, 2026.

Planned completion: Dec 31, 2026. Time left: 2 months

Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 3280), which also shows the latest inspection date and photos.

Facts

Status
Under construction
Official progress
1.01%, as published by the Dubai Land Department
Planned completion
Dec 31, 2026
Construction start
Jan 1, 2025
Units
125
Buildings
1
Developer
Dugasta Properties Development
Master developer
Nakheel .(P J S C)
Community
International City Phase 3, in DLD's area Warsan Fourth
Escrow bank
Abu Dhabi Commercial Bank
DLD project number
3280

The register describes it as: "(B+G+P+6+R) Residential Building.The project designed to have a concrete structure and block with internal and external finishes."

Progress as the register reported it

SinceProgressPlanned completion
Oct 29, 20261.01%Dec 31, 2026

Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.

Off-plan sales registered

99 off-plan sales in Moonsa Residences 2 have been registered with the Dubai Land Department, worth AED 64 million in all, the first on Feb 13, 2025 and the latest on Oct 19, 2026. 3 of them in the last 90 days. The median price over the last 12 months was AED 16,684 per square meter (AED 1,550 per square foot).

Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.