A 99 is a building project in Dubai Land Residence Complex, Dubai, by Arabian Gulf Properties. The Dubai Land Department's register puts it at 47.83% complete, with planned completion on Oct 31, 2026.
Planned completion was Oct 31, 2026. Time since: 7 days
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 2768), which also shows the latest inspection date and photos.
Facts
- Status
- Past planned completion
- Official progress
- 47.83%, as published by the Dubai Land Department
- Planned completion
- Oct 31, 2026
- Construction start
- Oct 31, 2023
- Units
- 90
- Buildings
- 1
- Developer
- Arabian Gulf Properties
- Master developer
- Dubai Land Residences
- Community
- Dubai Land Residence Complex, in DLD's area Wadi Al Safa 5
- Escrow bank
- United Bank Limited (management Office)
- DLD project number
- 2768
The register describes it as: "Residential (G+13F+R)"
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Oct 29, 2026 | 47.83% | Oct 31, 2026 |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
Off-plan sales registered
89 off-plan sales in A 99 have been registered with the Dubai Land Department, worth AED 109 million in all, the first on Jan 13, 2025 and the latest on Aug 20, 2026. 1 of them in the last 90 days. The median price over the last 12 months was AED 11,161 per square meter (AED 1,037 per square foot).
Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.
More in Dubai Land Residence Complex
- Peace Lagoons by Peace Homes Dubai Land Residence Complex · Peace Homes 4.16%Planned completion Sep 30, 2028
- Samana IVY Gardens 2 Dubai Land Residence Complex · Samana 20.03%Planned completion Dec 31, 2027
- Peace Lagoons II by Peace Homes Dubai Land Residence Complex · Peace Homes 4.04%Planned completion Jan 1, 2029
- Cove Living Residence by Imtiaz Dubai Land Residence Complex · Imtiaz 47.21%Planned completion Apr 15, 2027
- Sky Line by Peace Homes Dubai Land Residence Complex · Peace Homes 0%Planned completion May 30, 2030
- Samana Boulevard Heights Dubai Land Residence Complex · Samana 2.5%Planned completion Dec 31, 2028