37.69%complete

The Corner

The Corner is a building project in Dubai Land Residence Complex, Dubai, by Arabian Gulf Properties. The Dubai Land Department's register puts it at 37.69% complete, with planned completion on Jun 30, 2027.

Planned completion: Jun 30, 2027. Time left: 8 months

Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 2904), which also shows the latest inspection date and photos.

Facts

Status
Under construction
Official progress
37.69%, as published by the Dubai Land Department
Planned completion
Jun 30, 2027
Construction start
Sep 1, 2024
Units
126
Buildings
1
Developer
Arabian Gulf Properties
Master developer
Dubai Land Residences
Community
Dubai Land Residence Complex, in DLD's area Wadi Al Safa 5
Escrow bank
Mashreq Bank Psc
DLD project number
2904

The register describes it as: "Residential (B+G+ 7 Floors)"

Progress as the register reported it

SinceProgressPlanned completion
Oct 29, 202637.69%Jun 30, 2027

Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.

Off-plan sales registered

96 off-plan sales in The Corner have been registered with the Dubai Land Department, worth AED 100 million in all, the first on Oct 23, 2025 and the latest on Oct 27, 2026. 3 of them in the last 90 days. The median price over the last 12 months was AED 11,737 per square meter (AED 1,090 per square foot).

Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.

More in Dubai Land Residence Complex

More by Arabian Gulf Properties