Facts
- Status
- Under construction
- Official progress
- 11.06%, as published by the Dubai Land Department
- Planned completion
- Jul 31, 2029
- Construction start
- Jun 10, 2025
- Units
- 479
- Buildings
- 1
- Developer
- Dubai Creek Harbour
- Community
- Dubai Creek Harbour, in DLD's area Al Khairan First
- Escrow bank
- Emirates NBD Bank
- DLD project number
- 3608
The register describes it as: "B+G+3P+53F+2MECH+R"
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Oct 29, 2026 | 11.06% | Jul 31, 2029 |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
Off-plan sales registered
453 off-plan sales in Altan have been registered with the Dubai Land Department, worth AED 1.27 billion in all, the first on May 9, 2025 and the latest on Oct 27, 2026. 3 of them in the last 90 days. The median price over the last 12 months was AED 24,777 per square meter (AED 2,302 per square foot).
Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.
More in Dubai Creek Harbour
- Creek Bay Dubai Creek Harbour · Dubai Creek Harbour 0.62%Planned completion Apr 30, 2030
- Creek Haven Dubai Creek Harbour · Dubai Creek Harbour 0.87%Planned completion Mar 31, 2030
- Palace Residences Creek Blue Dubai Creek Harbour · Dubai Creek Harbour 20.52%Planned completion Mar 31, 2029
- Lyvia by Palace Dubai Creek Harbour · Dubai Creek Harbour 4.77%Planned completion Jul 31, 2029
- Albero Dubai Creek Harbour · Dubai Creek Harbour 11%Planned completion Sep 30, 2029
- Montiva Dubai Creek Harbour · Dubai Creek Harbour 5.85%Planned completion Sep 30, 2029
More by Dubai Creek Harbour
- Silva Dubai Creek Harbour · Dubai Creek Harbour 10.16%Planned completion Sep 30, 2029
- Arlo Dubai Creek Harbour · Dubai Creek Harbour 35.42%No planned date in the register
- Address Residences l Dubai Creek Harbour Dubai Creek Harbour · Dubai Creek Harbour 26.44%Planned completion Jan 31, 2029
- Valo Dubai Creek Harbour · Dubai Creek Harbour 66.05%No planned date in the register
- Altus Dubai Creek Harbour · Dubai Creek Harbour 64.2%Planned completion Jan 31, 2029
- Aeon Dubai Creek Harbour · Dubai Creek Harbour 90.04%No planned date in the register