Altus
Altus is a building project in Dubai Creek Harbour, Dubai, by Dubai Creek Harbour. The Dubai Land Department's register puts it at 64.2% complete, with planned completion on Jan 31, 2029.
Planned completion: Jan 31, 2029. Time left: 2 years 3 months
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 3184), which also shows the latest inspection date and photos.
Facts
- Status
- Under construction
- Official progress
- 64.2%, as published by the Dubai Land Department
- Planned completion
- Jan 31, 2029
- Construction start
- Dec 3, 2024
- Units
- 283
- Buildings
- 2
- Developer
- Dubai Creek Harbour
- Community
- Dubai Creek Harbour, in DLD's area Al Khairan First
- Escrow bank
- Mashreq Bank Psc
- DLD project number
- 3184
The register describes it as: "The project is composed of G+2P+2 residential towers Tower 1: 20 Res floors + Roof on Top Tower 2: 13 Res floors + Roof on Top Having a total of 280 units + 3 retail units"
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Oct 29, 2026 | 64.2% | Jan 31, 2029 |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
Off-plan sales registered
302 off-plan sales in Altus have been registered with the Dubai Land Department, worth AED 765 million in all, the first on Aug 30, 2024 and the latest on Nov 3, 2026. 10 of them in the last 90 days. The median price over the last 12 months was AED 25,792 per square meter (AED 2,396 per square foot).
Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.
More in Dubai Creek Harbour
- Creek Bay Dubai Creek Harbour · Dubai Creek Harbour 0.62%Planned completion Apr 30, 2030
- Creek Haven Dubai Creek Harbour · Dubai Creek Harbour 0.87%Planned completion Mar 31, 2030
- Palace Residences Creek Blue Dubai Creek Harbour · Dubai Creek Harbour 20.52%Planned completion Mar 31, 2029
- Lyvia by Palace Dubai Creek Harbour · Dubai Creek Harbour 4.77%Planned completion Jul 31, 2029
- Altan Dubai Creek Harbour · Dubai Creek Harbour 11.06%Planned completion Jul 31, 2029
- Albero Dubai Creek Harbour · Dubai Creek Harbour 11%Planned completion Sep 30, 2029
More by Dubai Creek Harbour
- Montiva Dubai Creek Harbour · Dubai Creek Harbour 5.85%Planned completion Sep 30, 2029
- Silva Dubai Creek Harbour · Dubai Creek Harbour 10.16%Planned completion Sep 30, 2029
- Arlo Dubai Creek Harbour · Dubai Creek Harbour 35.42%No planned date in the register
- Address Residences l Dubai Creek Harbour Dubai Creek Harbour · Dubai Creek Harbour 26.44%Planned completion Jan 31, 2029
- Valo Dubai Creek Harbour · Dubai Creek Harbour 66.05%No planned date in the register