Amal Tower
Amal Tower is a building project in Dubai Sports City, Dubai, by Consolidated Urban Real Estate Development Co. The Dubai Land Department's register puts it at 100% complete (completed), with planned completion on Jan 7, 2025.
Completed on Jan 7, 2025, against a planned date of Jan 7, 2025.
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 591), which also shows the latest inspection date and photos.
Facts
- Status
- Completed
- Official progress
- 100%, as published by the Dubai Land Department
- Planned completion
- Jan 7, 2025
- Construction start
- Aug 30, 2015
- Units
- 342
- Buildings
- 1
- Developer
- Consolidated Urban Real Estate Development Co
- Master developer
- Dubai Sports City
- Community
- Dubai Sports City, in DLD's area Al Hebiah Fourth
- Escrow bank
- Dubai Islamic Bank
- DLD project number
- 591
The register describes it as: "Freehold residential building development located in Dubai Sports City, the building is designed to have 2B+G+24+HC floors. The building is being constructed as a concrete structure with external and internal finishes."
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Oct 29, 2026 | 100% | Jan 7, 2025 |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
Off-plan sales registered
203 off-plan sales in Amal Tower have been registered with the Dubai Land Department, worth AED 146 million in all, the first on Jun 7, 2010 and the latest on Feb 26, 2025.
Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.
More in Dubai Sports City
- Sportz by Danube Dubai Sports City · Danube 80.22%Planned Mar 30, 2026, 7 months ago
- Lime Light Twin Towers Dubai Sports City · Lime Light Real Estate Development 71.09%Planned Jun 30, 2026, 4 months ago
- ASPIRZ by Danube Dubai Sports City · Danube 5.08%Planned completion Dec 31, 2028
- Mars Residences Dubai Sports City · Mars Star Real Estate Development 79.91%Planned Mar 23, 2024, 2 years 8 months ago
- Binghatti Haven Dubai Sports City · Binghatti 76.13%Planned Mar 31, 2026, 7 months ago