Azizi Amber
Azizi Amber is a building project in Al Furjan, Dubai, by Azizi Developments. The Dubai Land Department's register puts it at 100% complete (completed), with planned completion on Jul 31, 2025.
Completed on Jul 31, 2025, against a planned date of Jul 31, 2025.
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 2624), which also shows the latest inspection date and photos.
Facts
- Status
- Completed
- Official progress
- 100%, as published by the Dubai Land Department
- Planned completion
- Jul 31, 2025
- Construction start
- Mar 23, 2023
- Units
- 115
- Buildings
- 1
- Developer
- Azizi Developments
- Master developer
- Alfurjan ( L.L.C )
- Community
- Al Furjan, in DLD's area Jabal Ali First
- Escrow bank
- Abu Dhabi Commercial Bank
- DLD project number
- 2624
The register describes it as: "(B+G+2P+with Swimming Pool+8+R)With Retail at GF.The project designed to have a concrete structure and block with internal and external finishes."
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Oct 29, 2026 | 100% | Jul 31, 2025 |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
Off-plan sales registered
92 off-plan sales in Azizi Amber have been registered with the Dubai Land Department, worth AED 88.7 million in all, the first on Dec 25, 2023 and the latest on Apr 8, 2025.
Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.
More in Al Furjan
- SPARKLZ by Danube Al Furjan · Danube 7.75%Planned completion May 31, 2028
- Azizi Jewel Al Furjan · Azizi 43.03%No planned date in the register
- Azizi Neila Al Furjan · Azizi 38.53%Planned completion Jul 30, 2027
- The Stella Residences Al Furjan · Algouta Properties 71.06%Planned Dec 1, 2025, 11 months ago
- Azizi Sikander Al Furjan · Azizi 2%Planned completion Jun 17, 2027
- Raffi by Azizi Al Furjan · Azizi 2%Planned completion Jan 15, 2028
More by Azizi
- Azizi Venice 14 Dubai World Central · Azizi 30.29%Planned May 30, 2026, 5 months ago
- Azizi Venice 6 Dubai World Central · Azizi 11.58%Planned completion Dec 31, 2027
- Azizi Milan Heights City of Arabia · Azizi 0%Planned completion Sep 8, 2028
- Azizi Venice 7 Dubai World Central · Azizi 29.19%Planned Jan 28, 2026, 9 months ago
- Azizi Venice 13 Dubai World Central · Azizi 45.87%Planned completion Sep 16, 2027
- Azizi Venice 15 Dubai World Central · Azizi 0%Planned completion May 30, 2027