60.92%complete

Azizi Riviera 50

Azizi Riviera 50 is a building project in Meydan One Community, Dubai, by Azizi Developments. The Dubai Land Department's register puts it at 60.92% complete, with planned completion on Mar 13, 2027.

Planned completion: Mar 13, 2027. Time left: 4 months

Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 3614), which also shows the latest inspection date and photos.

Facts

Status
Under construction
Official progress
60.92%, as published by the Dubai Land Department
Planned completion
Mar 13, 2027
Construction start
Mar 13, 2025
Units
234
Buildings
1
Developer
Azizi Developments
Master developer
Meydan Group
Community
Meydan One Community, in DLD's area Al Merkadh
Escrow bank
Abu Dhabi Commercial Bank
DLD project number
3614

The register describes it as: "3B+G+15+R Residential and Commercial. The project designed to have a concrete structure and block with internal and external finishes."

Progress as the register reported it

SinceProgressPlanned completion
Oct 29, 202660.92%Mar 13, 2027

Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.

Off-plan sales registered

79 off-plan sales in Azizi Riviera 50 have been registered with the Dubai Land Department, worth AED 151 million in all, the first on Nov 7, 2025 and the latest on Nov 3, 2026. 12 of them in the last 90 days. The median price over the last 12 months was AED 24,850 per square meter (AED 2,309 per square foot).

Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.