63.48%complete

Azizi Venice 5

Azizi Venice 5 is a building project in Dubai World Central, Dubai, by Azizi Developments. The Dubai Land Department's register puts it at 63.48% complete, with planned completion on Oct 30, 2025.

Planned completion was Oct 30, 2025. Time since: 1 year

Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 2822), which also shows the latest inspection date and photos.

Facts

Status
Past planned completion
Official progress
63.48%, as published by the Dubai Land Department
Planned completion
Oct 30, 2025
Construction start
Oct 13, 2023
Units
484
Buildings
2
Developer
Azizi Developments
Master developer
Dubai Aviation City Corporation
Community
Dubai World Central, in DLD's area Madinat Al Mataar
Escrow bank
Bank of Sharjah
DLD project number
2822

The register describes it as: "RESIDENTIAL & COMMERCIAL (with retails) :Tower A : 3B+G+15+R+TR Tower B : 3B+G+16+R+TR ""

Progress as the register reported it

SinceProgressPlanned completion
Oct 29, 202663.48%Oct 30, 2025

Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.

Off-plan sales registered

348 off-plan sales in Azizi Venice 5 have been registered with the Dubai Land Department, worth AED 285 million in all, the first on Aug 15, 2024 and the latest on Nov 5, 2026. 90 of them in the last 90 days. The median price over the last 12 months was AED 17,870 per square meter (AED 1,660 per square foot).

Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.