Club Place
Club Place is a building project in Dubai Hills Estate, Dubai, by Dubai Hills Estate. The Dubai Land Department's register puts it at 68.82% complete, with planned completion on Dec 31, 2028.
Planned completion: Dec 31, 2028. Time left: 2 years 2 months
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 3197), which also shows the latest inspection date and photos.
Facts
- Status
- Under construction
- Official progress
- 68.82%, as published by the Dubai Land Department
- Planned completion
- Dec 31, 2028
- Construction start
- Sep 10, 2024
- Units
- 473
- Buildings
- 3
- Developer
- Dubai Hills Estate
- Community
- Dubai Hills Estate, in DLD's area Hadaeq Sheikh Mohammed Bin Rashid
- Escrow bank
- Emirates NBD Bank
- DLD project number
- 3197
The register describes it as: "Residential Building with Tower A (B+G+P+20+R) Tower B (B+G+P+17+R) Total Residential Units 473 numbers"
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Oct 29, 2026 | 68.82% | Dec 31, 2028 |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
Off-plan sales registered
492 off-plan sales in Club Place have been registered with the Dubai Land Department, worth AED 1.19 billion in all, the first on Aug 23, 2024 and the latest on Oct 26, 2026. 14 of them in the last 90 days. The median price over the last 12 months was AED 24,841 per square meter (AED 2,308 per square foot).
Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.
More in Dubai Hills Estate
- Palace Residences Dubai Hills Estate Dubai Hills Estate · Dubai Hills Estate 50.72%Planned completion Apr 30, 2028
- Park Lane Dubai Hills Estate · Dubai Hills Estate 55.39%Planned completion Oct 31, 2028
- Vida Residences Club Point Dubai Hills Estate · Dubai Hills Estate 43.52%Planned completion Feb 28, 2029
- Address Residences l Dubai Hills Estate Dubai Hills Estate · Dubai Hills Estate 26.48%Planned completion Feb 28, 2029
- Rosehill Dubai Hills Estate · Dubai Hills Estate 7.83%Planned completion Jun 30, 2029
- Vida Residences Hillside Dubai Hills Estate · Dubai Hills Estate 10%Planned completion May 31, 2029
More by Dubai Hills Estate
- Greenside Residence Dubai Hills Estate · Dubai Hills Estate 93.32%No planned date in the register
- Parkwood Dubai Hills Estate · Dubai Hills Estate 15%Planned completion Jan 31, 2029
- Hillsedge Dubai Hills Estate · Dubai Hills Estate 25.55%Planned completion Jan 31, 2029
- Parkside Hills Dubai Hills Estate · Dubai Hills Estate 68.29%Planned completion Jun 30, 2028
- Palace Residences Hillside A Dubai Hills Estate · Dubai Hills Estate 7.87%Planned completion Jun 30, 2029
- Palace Residences Hillside B Dubai Hills Estate · Dubai Hills Estate 0%Planned completion Oct 31, 2029