Parkside Hills is a building project in Dubai Hills Estate, Dubai, by Dubai Hills Estate. The Dubai Land Department's register puts it at 68.29% complete, with planned completion on Jun 30, 2028.
Planned completion: Jun 30, 2028. Time left: 1 year 8 months
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 2741), which also shows the latest inspection date and photos.
Facts
- Status
- Under construction
- Official progress
- 68.29%, as published by the Dubai Land Department
- Planned completion
- Jun 30, 2028
- Construction start
- Dec 16, 2023
- Units
- 370
- Buildings
- 1
- Developer
- Dubai Hills Estate
- Community
- Dubai Hills Estate, in DLD's area Hadaeq Sheikh Mohammed Bin Rashid
- Escrow bank
- Emirates NBD Bank
- DLD project number
- 2741
The register describes it as: "Mid - Rise Residential Development (G+2P+18).The project designed to have a concrete structure and block with internal and external finishes."
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Oct 29, 2026 | 68.29% | Jun 30, 2028 |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
Off-plan sales registered
394 off-plan sales in Parkside Hills have been registered with the Dubai Land Department, worth AED 871 million in all, the first on Apr 1, 2024 and the latest on Oct 2, 2026. 5 of them in the last 90 days. The median price over the last 12 months was AED 22,942 per square meter (AED 2,131 per square foot).
Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.
More in Dubai Hills Estate
- Palace Residences Dubai Hills Estate Dubai Hills Estate · Dubai Hills Estate 50.72%Planned completion Apr 30, 2028
- Park Lane Dubai Hills Estate · Dubai Hills Estate 55.39%Planned completion Oct 31, 2028
- Vida Residences Club Point Dubai Hills Estate · Dubai Hills Estate 43.52%Planned completion Feb 28, 2029
- Address Residences l Dubai Hills Estate Dubai Hills Estate · Dubai Hills Estate 26.48%Planned completion Feb 28, 2029
- Rosehill Dubai Hills Estate · Dubai Hills Estate 7.83%Planned completion Jun 30, 2029
- Vida Residences Hillside Dubai Hills Estate · Dubai Hills Estate 10%Planned completion May 31, 2029
More by Dubai Hills Estate
- Greenside Residence Dubai Hills Estate · Dubai Hills Estate 93.32%No planned date in the register
- Parkwood Dubai Hills Estate · Dubai Hills Estate 15%Planned completion Jan 31, 2029
- Club Place Dubai Hills Estate · Dubai Hills Estate 68.82%Planned completion Dec 31, 2028
- Hillsedge Dubai Hills Estate · Dubai Hills Estate 25.55%Planned completion Jan 31, 2029
- Palace Residences Hillside A Dubai Hills Estate · Dubai Hills Estate 7.87%Planned completion Jun 30, 2029
- Palace Residences Hillside B Dubai Hills Estate · Dubai Hills Estate 0%Planned completion Oct 31, 2029