100%complete

Condor Golf Links 18

Condor Golf Links 18 is a building project in Dubai Sports City, Dubai, by Condor Golf Links 18 Real Estate Development. The Dubai Land Department's register puts it at 100% complete (completed), with planned completion on Jun 30, 2026.

Completed on Jan 19, 2026, against a planned date of Jun 30, 2026.

Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 3350), which also shows the latest inspection date and photos.

Facts

Status
Completed
Official progress
100%, as published by the Dubai Land Department
Planned completion
Jun 30, 2026
Construction start
Sep 1, 2024
Units
256
Buildings
1
Developer
Condor Golf Links 18 Real Estate Development
Master developer
Dubai Sports City
Community
Dubai Sports City, in DLD's area Al Hebiah Fourth
DLD project number
3350

The register describes it as: "Residential Building (2B+G+14+R).The project designed to have a concrete structure and block with internal and external finishes."

Progress as the register reported it

SinceProgressPlanned completion
Oct 29, 2026100%Jun 30, 2026

Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.

Off-plan sales registered

223 off-plan sales in Condor Golf Links 18 have been registered with the Dubai Land Department, worth AED 222 million in all, the first on Mar 5, 2025 and the latest on Jan 9, 2026. The median price over the last 12 months was AED 20,055 per square meter (AED 1,863 per square foot).

Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.