20.2%complete

Cotier House 2 by Imtiaz

Cotier House 2 by Imtiaz is a building project in Palm Deira, Dubai, by Imtiaz Ug Real Estate Development. The Dubai Land Department's register puts it at 20.2% complete, with planned completion on Apr 15, 2027.

Planned completion: Apr 15, 2027. Time left: 5 months

Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 3671), which also shows the latest inspection date and photos.

Facts

Status
Under construction
Official progress
20.2%, as published by the Dubai Land Department
Planned completion
Apr 15, 2027
Construction start
Apr 15, 2025
Units
128
Buildings
1
Developer
Imtiaz Ug Real Estate Development
Master developer
Nakheel .(P J S C)
Community
Palm Deira
Escrow bank
First Abu Dhabi Bank
DLD project number
3671

The register describes it as: "G+2P+10+R Residential Building"

Progress as the register reported it

SinceProgressPlanned completion
Oct 29, 202620.2%Apr 15, 2027

Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.

Off-plan sales registered

109 off-plan sales in Cotier House 2 by Imtiaz have been registered with the Dubai Land Department, worth AED 363 million in all, the first on Jun 17, 2025 and the latest on Jun 4, 2026. The median price over the last 12 months was AED 28,180 per square meter (AED 2,618 per square foot).

Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.

More in Palm Deira