100%complete

Creek Palace

Creek Palace is a building project in Dubai Creek Harbour, Dubai, by The Lagoons Phase One. The Dubai Land Department's register puts it at 100% complete (completed), with planned completion on Mar 31, 2026.

Completed on Mar 31, 2026, against a planned date of Mar 31, 2026.

Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 2191), which also shows the latest inspection date and photos.

Facts

Status
Completed
Official progress
100%, as published by the Dubai Land Department
Planned completion
Mar 31, 2026
Construction start
Jan 16, 2020
Units
337
Buildings
1
Developer
The Lagoons Phase One
Community
Dubai Creek Harbour, in DLD's area Al Khairan First
Escrow bank
Emirates NBD Bank
DLD project number
2191

The register describes it as: "3Basements + Ground + 33 Store + Roof (Single Tower)"

Progress as the register reported it

SinceProgressPlanned completion
Oct 29, 2026100%Mar 31, 2026

Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.

Off-plan sales registered

412 off-plan sales in Creek Palace have been registered with the Dubai Land Department, worth AED 808 million in all, the first on Apr 12, 2022 and the latest on Nov 21, 2024.

Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.