The Acres 3 & Estates
The Acres 3 & Estates is a villa project in Wadi Al Safa 7, Dubai, by Dhre 2 Bts. The Dubai Land Department's register puts it at 14.87% complete, with planned completion on Nov 19, 2027.
Planned completion: Nov 19, 2027. Time left: 1 year
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 3126), which also shows the latest inspection date and photos.
Facts
- Status
- Under construction
- Official progress
- 14.87%, as published by the Dubai Land Department
- Planned completion
- Nov 19, 2027
- Construction start
- Nov 19, 2024
- Developer
- Dhre 2 Bts
- Community
- Wadi Al Safa 7
- Escrow bank
- Abu Dhabi Commercial Bank
- DLD project number
- 3126
The register describes it as: "Consists of 291 Villas (G+1, G+2); 3, 4, 5, 6 & 7- Bedrooms Villas; including 16 frozen plots as listed below. LOCI and U+A are the project?s architects : LOCI: G+1 = 36 Villas, and G+2 = 7 villas , including 5 frozen plots. U+A: G+1 = 104 Villas, and G+2 = 144 Villas, including 11 frozen plots."
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Oct 29, 2026 | 14.87% | Nov 19, 2027 |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
More in Wadi Al Safa 7
More by Dhre 2 Bts
- Jumeirah Residences Emirates Towers Trade Center Second · Dhre 2 Bts 4.22%Planned completion Sep 1, 2030
- Bluewaters Bay Marsa Dubai · Dhre 2 Bts 36.97%Planned completion Mar 1, 2027
- Design Quarter Business Park · Dhre 2 Bts 40.81%Planned completion Feb 25, 2027
- THE EDIT at d3 Business Park · Dhre 2 Bts 0.24%Planned completion Jan 31, 2030
- Atelis at d3 Business Park · Dhre 2 Bts 1.44%Planned completion Aug 14, 2029
- Bulgari Lighthouse Dubai Jumeira Bay · Dhre 2 Bts 80.01%Planned completion Mar 27, 2027