Eden Garden
Eden Garden is a building project in Dubai Sports City, Dubai, by Lokhandwala Builders International. The Dubai Land Department's register puts it at 96.02% complete, with planned completion on Aug 31, 2022.
Planned completion was Aug 31, 2022. Time since: 4 years 2 months
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 510), which also shows the latest inspection date and photos.
Facts
- Status
- Past planned completion
- Official progress
- 96.02%, as published by the Dubai Land Department
- Planned completion
- Aug 31, 2022
- Construction start
- May 5, 2008
- Units
- 394
- Buildings
- 1
- Developer
- Lokhandwala Builders International
- Master developer
- Dubai Sports City
- Community
- Dubai Sports City, in DLD's area Al Hebiah Fourth
- Escrow bank
- Bank of Baroda
- DLD project number
- 510
The register describes it as: "Residential tower development located within Sport City. The building has 2 basements + ground and 4 podium levels which will provide car parking and will provide a mixture of studio, 1, 2 and 3 bedroom units on the upper 25 floors.(2B+G+4P+25)"
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Oct 29, 2026 | 96.02% | Aug 31, 2022 |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
Off-plan sales registered
323 off-plan sales in Eden Garden have been registered with the Dubai Land Department, worth AED 185 million in all, the first on Jun 29, 2009 and the latest on Feb 25, 2026. The median price over the last 12 months was AED 8,049 per square meter (AED 748 per square foot).
Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.
More in Dubai Sports City
- Sportz by Danube Dubai Sports City · Danube 80.22%Planned Mar 30, 2026, 7 months ago
- Lime Light Twin Towers Dubai Sports City · Lime Light Real Estate Development 71.09%Planned Jun 30, 2026, 4 months ago
- ASPIRZ by Danube Dubai Sports City · Danube 5.08%Planned completion Dec 31, 2028
- Mars Residences Dubai Sports City · Mars Star Real Estate Development 79.91%Planned Mar 23, 2024, 2 years 8 months ago
- Binghatti Haven Dubai Sports City · Binghatti 76.13%Planned Mar 31, 2026, 7 months ago
- The First Collection at Dubai Sports City Dubai Sports City · Tfg International Real Estate Development 65.7%Planned completion Nov 30, 2027