3.67%complete

Golf Hills

Golf Hills is a building project in Dubai World Central, Dubai, by Emaar Dubai South DWC. The Dubai Land Department's register puts it at 3.67% complete, with planned completion on Sep 30, 2029.

Planned completion: Sep 30, 2029. Time left: 2 years 11 months

Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 4117), which also shows the latest inspection date and photos.

Facts

Status
Under construction
Official progress
3.67%, as published by the Dubai Land Department
Planned completion
Sep 30, 2029
Construction start
Dec 30, 2025
Units
204
Buildings
1
Developer
Emaar Dubai South DWC
Community
Dubai World Central, in DLD's area Madinat Al Mataar
Escrow bank
First Abu Dhabi Bank
DLD project number
4117

The register describes it as: "G+P+10 Floors Residential Building"

Progress as the register reported it

SinceProgressPlanned completion
Oct 29, 20263.67%Sep 30, 2029

Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.

Off-plan sales registered

166 off-plan sales in Golf Hills have been registered with the Dubai Land Department, worth AED 254 million in all, the first on Nov 26, 2025 and the latest on Jun 22, 2026. The median price over the last 12 months was AED 17,320 per square meter (AED 1,609 per square foot).

Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.

More in Dubai World Central

More by Emaar