Island Park I
Island Park I is a building project in Dubai Creek Harbour, Dubai, by The Lagoons Phase One. The Dubai Land Department's register puts it at 100% complete (completed), with planned completion on Feb 24, 2025.
Completed on Feb 24, 2025, against a planned date of Feb 24, 2025.
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 1895), which also shows the latest inspection date and photos.
Facts
- Status
- Completed
- Official progress
- 100%, as published by the Dubai Land Department
- Planned completion
- Feb 24, 2025
- Construction start
- Aug 15, 2017
- Units
- 160
- Buildings
- 1
- Developer
- The Lagoons Phase One
- Community
- Dubai Creek Harbour, in DLD's area Al Khairan First
- Escrow bank
- Dubai Islamic Bank
- DLD project number
- 1895
The register describes it as: "2B+G+10F Residential+Retail , The project designed to have a concrete structure and block with internal and external finishes."
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Oct 29, 2026 | 100% | Feb 24, 2025 |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
Off-plan sales registered
151 off-plan sales in Island Park I have been registered with the Dubai Land Department, worth AED 294 million in all, the first on Jan 30, 2018 and the latest on Dec 20, 2022.
Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.
More in Dubai Creek Harbour
- Creek Bay Dubai Creek Harbour · Dubai Creek Harbour 0.62%Planned completion Apr 30, 2030
- Creek Haven Dubai Creek Harbour · Dubai Creek Harbour 0.87%Planned completion Mar 31, 2030
- Palace Residences Creek Blue Dubai Creek Harbour · Dubai Creek Harbour 20.52%Planned completion Mar 31, 2029
- Lyvia by Palace Dubai Creek Harbour · Dubai Creek Harbour 4.77%Planned completion Jul 31, 2029
- Altan Dubai Creek Harbour · Dubai Creek Harbour 11.06%Planned completion Jul 31, 2029
- Albero Dubai Creek Harbour · Dubai Creek Harbour 11%Planned completion Sep 30, 2029