Luxury Family Residence III
Luxury Family Residence III is a building project in Business Bay, Dubai, by Kappa Acca Real Estate Development. The Dubai Land Department's register puts it at 50.6% complete, with planned completion on Jun 30, 2025.
Planned completion was Jun 30, 2025. Time since: 1 year 4 months
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 2477), which also shows the latest inspection date and photos.
Facts
- Status
- Past planned completion
- Official progress
- 50.6%, as published by the Dubai Land Department
- Planned completion
- Jun 30, 2025
- Construction start
- Jun 30, 2022
- Units
- 72
- Buildings
- 1
- Developer
- Kappa Acca Real Estate Development
- Master developer
- Business Bay
- Community
- Business Bay
- Escrow bank
- Arab Bank For Investment & Foreign Trade Almasref
- DLD project number
- 2477
The register describes it as: "Residential-Apartment + Commercial-Retail (1B+G+3P+18F+R).The project designed to have a concrete structure and block with internal and external finishes."
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Oct 29, 2026 | 50.6% | Jun 30, 2025 |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
Off-plan sales registered
25 off-plan sales in Luxury Family Residence III have been registered with the Dubai Land Department, worth AED 440 million in all, the first on May 17, 2023 and the latest on Oct 15, 2026. 1 of them in the last 90 days. The median price over the last 12 months was AED 39,679 per square meter (AED 3,686 per square foot).
Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.
More in Business Bay
- Binghatti Skyrise Business Bay · Binghatti 35.89%Planned completion Dec 31, 2026
- Al Habtoor Tower Business Bay · Al Habtoor 90.01%Planned completion Dec 31, 2026
- Binghatti Aquarise Business Bay · Binghatti 21.04%Planned Oct 31, 2026, 7 days ago
- Bayz 101 by Danube Business Bay · Danube 10%No planned date in the register
- Aykon City 3 Business Bay · Damac 31.35%Planned completion Dec 30, 2027
- Bayz 102 by Danube Business Bay · Danube 6.52%Planned completion Dec 31, 2029