100%complete

Marina Living

Marina Living is a building project in Dubai Marina, Dubai, by Continental Investments Lmd. The Dubai Land Department's register puts it at 100% complete (completed), with planned completion on Jun 30, 2025.

Completed on Jan 14, 2026, against a planned date of Jun 30, 2025.

Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 2540), which also shows the latest inspection date and photos.

Facts

Status
Completed
Official progress
100%, as published by the Dubai Land Department
Planned completion
Jun 30, 2025
Construction start
Jan 15, 2023
Units
205
Buildings
1
Developer
Continental Investments Lmd
Master developer
Emaar Properties
Community
Dubai Marina, in DLD's area Marsa Dubai
DLD project number
2540

The register describes it as: "As per IMS :- G+2P+19 and As per BP :- G+2P+20+2R ,Residential,The project designed to have a concrete structure and block with internal and external finishes."

Progress as the register reported it

SinceProgressPlanned completion
Oct 29, 2026100%Jun 30, 2025

Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.

Off-plan sales registered

225 off-plan sales in Marina Living have been registered with the Dubai Land Department, worth AED 418 million in all, the first on Jan 19, 2023 and the latest on Jan 8, 2026. The median price over the last 12 months was AED 23,740 per square meter (AED 2,206 per square foot).

Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.